Dependencies are set per-milestone (not per-case). You'll have to split those dependent tasks which depend on the non-FogBugz group out into their own milestone, get a delivery date for the spec, and set that as the start date for the milestone. This will allow you to see via EBS whether the non-FogBugz user is going to impact delivery date.