Feature request: an option to tell EBS to take unestimated cases into account

The main question is here. Okey, as recommended, i've learned to divide tasks by 3-8 hours length. I have a group estimation process. So now i'm entering new tasks and trying to …
6
votes
2answers
251 views

How does EBS works with not estimated tasks?

Does it take the into account at all? Does it take some average (random?) task length estimate for them? Does it take some average (random?) real task length? Please note, that …
0
votes
1answer
107 views

Feature request: provide EBS data on per-case basis

It's a common need of PM to know when particular task is going to be done. We have an estimate, the person working on (assigned to) the case. Can't we tell 5 / 50 / 95% predicted …
1
vote
1answer
269 views

The Burn Down report does not seem to be reporting properly

We're trying to implement Scrum with Fogbugz and use the burndown chart. To test this we've set up a few tasks to be delivered in a sprint ending in the future (9th April and star …
5
votes
1answer
372 views

How does EBS work with virtual users?

As recommended, we use virtual "up for grabs" user for scrum-like process. So here is the question: how does EBS work with the case when most of the work is assigned to a virtual …
10
votes
3answers
345 views

Adding subcase and taking time away from parent cases original time estimate

The FogBugz Project Planning page on Outline Tasks states: Creating a detailed project outline is fast and simple in FogBugz. You can create a high-level case for each feature …
0
votes
1answer
163 views

Feature request (big): another way of EBS to better handle project multitasking

The main information is contained in following question:http://fogbugz.stackexchange.com/questions/1199/does-project-milestones-report-take-into-account-other-projects-work/1249#12 …