When one FogBugz user is logging their time to a Case that wasn't assigned to them (because they were assisting another FogBugz user assigned to that Case), it is actually taking off time from the Assigned developer.
For instance if the Assigned Developer had 15 hours estimated, and the FogBugz user who assisted the Developer logs in his time as 1 hour, it will show that the Assigned Developer has 14 hours remaining.
Why is that happening? How can we remove this problem?