I have created a project, assigned milestones and resources etc. but the 1% probability for completion is next year (although work on the project cases has already started) but the due date for completion is July 2010
what am I missing?
|
1
|
I have created a project, assigned milestones and resources etc. but the 1% probability for completion is next year (although work on the project cases has already started) but the due date for completion is July 2010 what am I missing? |
|||
|
|
|
1
|
A couple things that you may want to check. Under "My Settings => Working Schedule" make sure that your workday hours match what you plan to work and that the "% time spent on FogBugz tasks" matches what you plan to spend on the given task. If I change my schedule so that I'm work from 8am to 9am and take 1 hour lunch (even though it starts at noon), EBS says I'll never finish my tasks. |
||
|
|
|
0
|
Evidence-Based Scheduling will predict your ship date for a range of probabilities. The due date for the milestone you create is only a nominal date for you to manage the project, and also to put the milestones in order for display (and for EBS to know what you are working on first). If you have further questions about how to use EBS, please email us. |
|||
|