The start date for my milestone is 4/1/2010, yet my burndown chart is showing activity from way back in 2009?
What's going on?!
|
4
|
The start date for my milestone is 4/1/2010, yet my burndown chart is showing activity from way back in 2009? What's going on?! |
|||||||||||
|
|
2
|
The current algorithm uses the first date any case in the milestone was worked on. As described in your answer, this can cause weirdness with the burndown chart. Maybe the burndown charts first data point should be the start date as defined by the milestone but show time burned up to that point. i.e. - Day 0 has two points with a vertical line connecting them. The top point is the original time remaining. The bottom point is the time remaining after burning hours worked before the milestone officially started. On Day 1 the chart begins its burn from the bottom Day 0 point. Obviously there would need to be some visual indicator that that Day 0 has some "pre-burn". :-) |
|||
|
|
|
1
|
After looking in the FogBugz didn't stop anyone from doing performing work on the milestone prior to its start date, and now that I think about it, I think that's okay. We want minimal friction. If I'm free and able to start on a milestone early, why block this? There is still an element of confusion here. Perhaps there's something that can be added to the burndown chart to make the above scenario clear. |
|||
|
|
1
|
Given the information in the above answers, one interim proposal would be to add a vertical line to the graph for the start date, in the style of the vertical line for the completion date. At least then people viewing the chart could mentally ignore anything before the start date, and you wouldn't have to change the agorithm too much. We're suffering quite a bit from the visual "messy preamble" to the start of the burndown chart. We have some cases added / worked on over a long time, and for example in a current milestone there was a case raised in 2007 which had some analysis time logged against it earlier this year. The "messy preamble" on the front of the chart is longer in weeks than the sprint is due to last. So the burn down chart looks like a "burn up" chart, with a sharp drop off at the end representing the actual sprint. I've asked around and we've no one here interested in anything appearing on a burn down chart before the start date of the milestone. |
|||
|