It seems that EBS doesn't account for cases that have a case deadline but are in a milestone with no deadline.
Example: I am looking at the report for a milestone due 4/23. Then, as a test, I added a dummy case to another project, milestone 'Undecided', with an estimate of 2 days and a deadline of 4/22. I expected see a noticeable change in my per-user completion date after refreshing the report for the 4/23 milestone, but I see no change.
Is there any way to get EBS to recognize that the dummy case has to be completed before the 4/23 milestone, since its deadline is 4/22?