If a developer is waiting on a non-developer type (who is not a licensed FogBugz user) i.e. Marketing, Business Development to complete something (let's say a Spec or a branding design) before he can begin developing but he is already working on cases for that Milestone, how do we account for those tasks that he is dependent upon?
|
2
|
Dependencies are set per-milestone (not per-case). You'll have to split those tasks which depend on the non-FogBugz group out into their own milestone, get a delivery date for the spec, and set that as the start date for the milestone. This will allow you to see via EBS whether the non-FogBugz user is going to impact delivery date. |
|||
|
|