We're very risk averse. We don't use the 50% lines in the Completion Date (Over Time) report or the Burn Down Charts.
- It would be great if we could select which probability points draw the lines in those reports. This is sort of already asked for in http://fogbugz.stackexchange.com/questions/1889/feature-request-configurable-probability-points I'm bringing it up again to clarify it for this situation and to provide context.
- It would also be great if we could choose which lines were the "thick" lines. Even if we don't get the ability to choose the probability points, it would really help if we could choose which lines showed most prominently on the reports. My management constantly keys in on the biggest lines and I have to explain to them that just because they're thicker, they're not more likely or important. We live by the 95% line over here and it would be nice if we could make that the most prominent line in the reports.