How to manage estimation time for R&D tasks - FogBugz Knowledge Exchange most recent 30 from http://fogbugz.stackexchange.com 2013-06-18T04:46:07Z http://fogbugz.stackexchange.com/feeds/question/10827 http://www.creativecommons.org/licenses/by-nc/2.5/rdf http://fogbugz.stackexchange.com/questions/10827/how-to-manage-estimation-time-for-rd-tasks How to manage estimation time for R&D tasks rold2007 2012-09-28T04:44:36Z 2012-09-28T04:44:36Z <p>I'm working in image processing and I often have R&amp;D tasks. Sometimes these tasks take a lot more time to do than estimated initially. For example, I recently estimated a task to take 6 hours and it finally took me more than 70 hours...</p> <p>What is the expected way to deal with these kind of task and EBS ? Am I supposed to set these tasks as "Scheduled tasks" so that they don't affect my estimation history ?</p>